Works include the complete Design Supply and Install of Electrical Systems in a two story multi room laboratory and study space. A Challenging project as we were given a design period of 6 weeks and onsite fit out period of 12 weeks.
The project was completed on time and within budget. The University design team expressed delight with the finished product and shared fantastic feedback from the staff